The Port Allegany
Union High School 1954
photo credit: Raymond Morton Hall:
"Raymond Viner Hall Architect"
Go Back
To Port Allegany Topo Map
The much needed new high school building was designed as a semi-integrated
extension of the existing recreational facilities with the intent of creating
a more pleasant school envioronment than usually obtains. A developing need
for expanded educational and recreational programs for adults as well as children
is recognized. As a result this major capital investment by the community
invites increased use during normally idle periods; and the taxpayers dollar
produces additional dividends of culture and health within the community.
The Port Allegany High School was built where the separate wings for Senior
and Junior High students relate to joint use facilities such as the shops,
cafeteria, library, and auditorium. The gym is placed next to the pool for
summer use of locker rooms. Noisy activities face away from the study places
and there is public access to any major facilities without having to enter
classrooms.
The High School was built in 1954 and was given additions in 1962. In 1954,
the construction costs (contracts) was $907,994 with a student capacity of
638 students. The area was 70,960 square feet. Then, in 1962, 16,600 square
feet more was added on, giving the high school a final student capacity of
839 students. The final cost was $l,421,917.
Scroll Down to see High School Plan
photo credit: Raymond Morton Hall:
"Raymond Viner Hall Architecture"
See 2005 View of High School